I am writing for the purpose of further information about environmental considerations in pipeline project in particular during monsoon, as seasons may have potential impact with both the bio-physical and socio-economic features within construction areas.
In general practice following measures will be implemented;
- Soil Erosion and Sediment Control;
- Dewatering of trench onto stable vegetated surface or into constructed containment ponds and water discharge preventive measures, etc.
I am looking more typically programs are to be undertaken during monsoon or any examples/lesson learnt from past projects, or came across with any saturated conditions.
I would be thankful for any information that you can provide me. Thank you very much in advance for helping me on this matter
Replies
Could you kindly clarify : what "pipeline project" are you referencing? What will the pipeline carry? From where to where? Oil and gas pipelines have a global record of failure and deadly, toxic spills, most of all right here, in the USA, heart and soul of the fossil fuel world pushers.
In any and every case, we dont need fossil fuel energy pipelines; we need solar and wind power for the most part and other locally available, locally manageable renewable energy sources.
Looking forward to learning more.
Many thank Mark. this is interesting to me.
Mark Sabolch said:
Thank you Mr. Sharath
Sharath Manohar Rao said:
Dear Rita,
I am asking about Pipeline Construction ...laying of pipeline ..underground..for Oil as well as NG.
rgds,
Rita Dixit Kubiak said:
Hi Vikram,
A lot of experience has been gained in managing soil erosion on construction sites. You may have seen an Australian publication on this issue, referred locally as the 'Blue Book' (see below for link). Such measures as:
Dealing with a lot of water in wet weather conditions is not easy. It has been the case in northern Australia, depending upon location and access, some projects are stopped in the 'wet' season and recommenced after the 'wet' because dealing with the boggy conditions may be counter-productive.
Let me know if you would like to know more.
Best wishes.
Mark Sabolch
http://www.landcom.com.au/news/publications-and-programs/the-blue-b...
Deearthed soil must be hauled atleast a meter away from the dug trench...
temporary pattis shud me laid to withstand the loose soil during pipe laying...
Vikram:
I just saw an email on this and was wondering what you are referring in regard to the pipeline project in the monsoon .............. is this pipeline project about extracting natural gas ............... are you talking about a pipeline to "frack" natural gas? Please do let me know what you are referring to..............